Exodus/SC-6 and 7

ExodusSC8

Location: Santa Clara

Features: Design/build data center facility development of approximately 330,385 SF.  Services include managing the programming of the facility, scheduling, budgeting, construction and commissioning of the facility.  Features of this facility include 24 Hitec Generators, 150,000 gallons of underground fuel, (2) - Two story concrete tilt-up buildings with steel structure attached by a common electrical room. This project also included the construction of a 60Kv electrical substation with all associated underground infrastructure.

 

For your next project call Gary Filizetti, President, Devcon 408-942-8200.